At Severn River Association (SRA) we help communities improve their local environment and restore the Severn River. Good communication is really important. This page will update you about what’s happening with the Severn Run Watershed Planning project. Please email Ben Fertig, ben@severnriver.org with questions. Click on any picture to make it bigger or to download.
SRA is a 501c3 non-profit organization with experience and success at pursuing funding and project management for pollution reduction and environmental restoration. Our vision is a thriving Severn River by 2050, and our mission is to connect the people who live, work, and play on the Severn River to restore and protect it for all of our communities.
This progress was originally identified in 2023. After a key property changed hands and delayed the project, SRA partnered with Underwood and Associates to pursue funding to perform an in-depth study of the watershed and determine the best possible approach for restoration of the Severn Run, as well as upstream practices to benefit local communities and reduce stormwater flow.
The primary goal of the project is to prevent further erosion within the incised stream channel of the Severn Run and ultimately the Severn River. A second goal is to identify opportunities for improved stormwater management within the subwatershed and strengthen the connection between nearby communities and the Severn Run Natural Environmental Area.
Here is the current identified area where the stream restoration will take place:
The overall goal of this project is to 1) correct the stream incision by reconnecting the floodplain of the stream and 2) protect the stream flowing into the Severn Run Natural Environmental Area from stormwater runoff. To achieve these goals, the primary objective of this project is to design and permit a comprehensive stream restoration that mimics a natural stream system and reduces water flow and treats the stormwater runoff pollution by slowing the water down.
SRA is seeking grant funding for this project. Funding could be awarded in full, in part, or not at all. If unsuccessful, SRA will try again. A ‘no’ is not final or forever.
There are four stages to the project:
Next steps include building community support, identifying stormwater management needs within the study area, completing project design and permitting, obtaining construction funding, implementing the restoration, and establishing maintenance plans.
SRA wants to make sure that the project is something that the community will enjoy (in addition to all the great environmental benefits). Keep in mind that, as with so many things in life, there are trade-offs to consider. We want to understand what you value so the project will reflect those values. So, right now we want your feedback, especially while the project is still in its early stages.
The early stages of the project – right now – is the best opportunity to make sure to get it right. Please let me know what you think. You can email me any time, ben@severnriver.org. As we get closer to a finished design, there will be less wiggle room to make changes. Once the design is 100% complete, it will be locked in and we won’t be able to make changes.
Here are preliminary design concepts for the stream restoration:
SRA will seek construction funding once 60% design is achieved and permits are requested through a combination of grant proposals submitted to the Whole Watershed Fund, Anne Arundel County (via Chesapeake Bay Trust), MD Department of Natural Resources (the Chesapeake and Atlantic Coastal Bays Trust Fund), and/or the National Fish and Wildlife Foundation (Small Watershed Grant).
For the first five years after construction, SRA will be responsible for routine and aesthetic maintenance of the project, as defined below. SRA anticipates contracting with Maryland Reentry Resource Center (www.mdrrc.org), and its sister organization GreenLift (www.greenlift.net), which provides wraparound services and job training for neighbors returning from incarceration so that they can successfully transition back home. After five years, responsibility for routine maintenance will be transferred to the property owners. Optionally, the community can contract with SRA or GreenLift to continue maintenance services.
Routine maintenance obligations are specified in the Memorandum of Understanding with the County and include:
September 2025 – Meet with Underwood and Associates and discuss potential steam restoration
November 2025 – SRA submit proposal for design and permitting to the Chesapeake Bay Trust Watershed Assistance Grant Program
Community support is critical to a successful grant proposal. Specifically, there are several ways you can choose to support this project. Any and all are appreciated!
If you are interested in participating in any of the ways above, please reach out to SRA’s Restoration Manager, Ben Fertig: ben@severnriver.org
Let SRA know your thoughts about the project. We will update this section with how these will be addressed.
Check out the Google Photo Album for photos of the sites. Photos will be added to track the progress.